Final F-35 development tunnel test completed

  • Published
  • By Philip Lorenz III
  • Arnold Engineering Development Center Public Affairs
Workers at the Arnold Engineering Development Center here conducted the final planned F-35 Lightning II Joint Strike Fighter pre-production development wind tunnel test Feb. 5, helping put the F-35 a step closer to manufacturing.

"This was the last developmental test at AEDC for all JSF variants prior to aircraft production," AEDC Air Force Project Manager 1st Lt. Ezra Caplan said. "It was the culmination of more than 8,600 hours and $50 million worth of wind tunnel testing the Joint Strike Fighter over the past five years - a significant achievement for AEDC. This aerodynamics test was the final entry in that series."

This test helped add new critical data for the Navy variant of the F-35, said Aerospace Testing Alliance Project Engineer Randy Hobbs.

"This particular test was about filling in the blanks other testing facilities hadn't obtained yet at the higher-end Mach numbers," he said. "The results from this test will go into the JSF program's aerodynamic database and complement the ground testing that will follow at Marietta, Georgia."

Marc Skelley, an Air Force project manager at the center, said testing done at AEDC and in Marietta is a collaborative effort.

"Our efforts are complementary and Lockheed Martin uses data taken at AEDC and from other facilities to complete the JSF aero database," he said. "Lockheed Martin has a large, low-speed wind tunnel in Marietta where they do stability and control testing at low speeds and with the landing gear down. Usually whatever test we did here was either preceded or followed by an entry down in Marietta."

Lieutenant Caplan said continuous improvements in testing methods and technology have resulted in significant reductions in cost and time.

"One of the benefits of testing here is that we're able to provide the data at near real time to the customer on site," he said. "This reduces the number of model configuration changes that would have been necessary in the past to get the quality of data they would need before pressing on with the test."

AEDC workers have tested the JSF in the center's wind tunnels and jet engine test cells for several years. The current multi-year test regimen for the aircraft's Pratt & Whitney (P&W) F135 jet engine is a $200-million program.

The center's role in supporting the JSF program dates back to 1997 when competing engine configurations were tested in propulsion test cells here. Aerodynamic and propulsion integration testing on the JSF began the same year when the two competing prototype aircraft, the X-35 and X-32, were tested at AEDC.

A busy schedule with the P&W F135 still lies ahead for center workers and some additional store separation testing also is planned for the near future.